Subscribe

Latest › Patna High Court › Civil › Property & Land › 20 August 2026

Patna High Court

Patna HC sets aside Caste Scrutiny Committee order holding petitioner Kamkar, not Kharwar, as no proper inquiry was held

Court
High Court of Judicature at Patna
Date of judgment
20 August 2026
Case
CWJC/16164/2023
Parties
Dinesh Prasad Kharwar Vs The State of Bihar
Bench
MR. JUSTICE RAJIV ROY
Outcome
Disposed of

The court's decision

The Court said the Caste Scrutiny Committee had completely erred in not conducting a proper inquiry. The points needing examination were: whether the petitioner, whose family shifted from Palamu (present Jharkhand) to Bihar, belongs to the Kamkar (extremely backward class) or the Kharwar (Scheduled Tribe) category; the statements of prominent persons of the locality and family members and the different certificates, set against revenue records showing Parahu Kamkar as a purchaser with his caste as Kamkar; and whether the Committee had ascertained that Parahu Kamkar is the petitioner's grandfather.

The Court noted that the petitioner had made it clear that he has nothing to do with Parahu Kamkar and that his ancestor bought the land from Ram Nath Kahar and Suraj Kahar, who in turn had bought it from Parahu Kamkar. That position was already on record in paragraph 5 of his reply to the counter affidavit.

The Court concluded that the Committee's finding needed interference and that it has to do the exercise once again so far as the caste of the petitioner is concerned. The Committee is duty bound to start the entire proceeding from scratch and decide whether the petitioner belongs to the Kamkar caste and/or the Kharwar caste.

The order vide memo no. 11711 dated 20.06.2023 issued by the Caste Scrutiny Committee was set aside, with liberty to start the proceeding against the petitioner and his family members in accordance with law. The writ petition was disposed of with those observations.

Summary

The Patna High Court has set aside an order of the Caste Scrutiny Committee which held that a Buxar resident belongs to the Kamkar caste, an extremely backward class, and not to the Kharwar caste, which falls in the Scheduled Tribe category. Justice Rajiv Roy held that the Committee had completely erred in not conducting proper enquiry on whether the petitioner is a Kamkar or a Kharwar, on the statements and certificates set against the revenue records, and on whether Parahu Kamkar is the petitioner's grandfather. The order was set aside with liberty to start the proceeding in accordance with law, and the Court observed that the Committee is duty bound to start the entire proceeding from scratch. The Court did not grant the prayer for a Kharwar caste certificate; the caste question is left to the Committee to decide afresh.

The petitioner, Dinesh Prasad Kharwar, said his family was originally from Palamu in undivided Bihar (now Jharkhand) and later moved to Bihar, and that his earlier certificates all showed his caste as Kharwar. After complaints, an inquiry was held and it was prima facie found that he was a Kamkar. The matter then went to the Caste Scrutiny Committee, which, after giving him an opportunity, concluded that he belongs to the Kamkar caste. This was communicated by memo no. 11711 dated 20.06.2023.

In the writ petition (CWJC No. 16164 of 2023) he sought quashing of that memo, which denied him a Kharwar caste certificate, and a direction to issue the certificate. The Court disposed of the petition on 20 August 2026 with the memo set aside and liberty to the authorities to proceed in accordance with law.

The question before the court

What each side argued

Read the full judgment (PDF) ↗

Official source: High Court of Judicature at Patna. The PDF above is a copy from an open dataset of the court's public records.

This summary is prepared for general assistance only. It may contain errors and is not legal advice — rely on the full judgment.

Writ JurisdictionCaste CertificateScheduled Tribe

Related judgments

Delhi High Court Allowed ·18 Nov 2026 ·Tort ★ Editor's pick

Two Children Die After Falling into Open Sewer in Park; Delhi HC Directs DDA and DJB to Pay Compensation

The question: Whether a writ petition for compensation for deaths in an open sewer was maintainable despite the objection of disputed questions of fact and the remedy of a civil suit

The Delhi High Court has allowed two connected writ petitions, filed separately by the respective parent of each of two boys who died on 16 April 2010 after slipping into an open sewer manhole in a DDA park at SU Block, near Double Tanki, Pitampura. Justice Jasmeet Singh held the Delhi Development Authority and the Delhi Jal Board negligent and jointly and severally liable to pay Rs. 11,01,000 (rounded off) in each petition, with 9% simple interest from the date of filing of the petitions, and Rs. 1,00,000 as costs in each petition. The Municipal Corporation of Delhi was held not liable. The children were about 11 and a half years and 12 years nine months old. A PCR call led to FIR No. 142/2010, registered under Section 304A of the Indian Penal Code, 1860. The MCD and the Delhi Jal Board first denied that the site fell within their jurisdiction. In a reply of 22 June 2011 the Delhi Jal Board said the site was an RCC chamber with a raised wall of 4 to 5 feet. The police later filed a cancellation report, which, according to the police respondents, the ACMM, Rohini Courts, accepted on 5 August 2013. The parents learnt of this in 2015, sent notices under Section 80 of the Code of Civil Procedure seeking Rs. 10,00,000 each, and filed the writ petitions in 2016. They sought compensation, interest and costs from the DDA, Delhi Jal Board, MCD, the Investigating Officer, the Commissioner of Police and the Ministry of Home Affairs. The petitions were heard together and judgment, reserved on 13 August 2026, was pronounced on 18 November 2026.

W.P.(C)/317/2016 (with W.P.(C) 284/2016)
Kerala High Court Allowed ·20 Nov 2026 ·Preventive Detention ★ Editor's pick

Article 22(5) Violated by Non-Supply of Detention Order in Malayalam and Failure to Consider Representation: Kerala HC

The question: Whether unexplained delay in issuing the detention order snapped the live link with the last prejudicial activity

The Kerala High Court has set aside an order of preventive detention passed under Section 3(1) of the Prevention of Illicit Traffic in Narcotic Drugs and Psychotropic Substances Act, 1988 (PITNDPS Act), and the Government order confirming it for one year. A Division Bench of Justice Anil K. Narendran and Justice Muralee Krishna S. held that the detention order was not supplied to the detenue in Malayalam, the language recorded in it as known to him, and that a representation sent to the Central Government by the petitioner, his wife, was never considered. Each lapse breached Article 22(5) of the Constitution. The petitioner, wife of the detenue, challenged Ext.P1 order dated 31.03.2026, issued by the Additional Chief Secretary to the Government under Section 3(1), and Ext.P2 order dated 16.09.2026, issued under Section 9(f) read with Section 11, confirming the detention for one year from the date of detention. She also sought a writ of habeas corpus for his release. The detenue was apprehended on 16.07.2026 and has been in detention since 17.07.2026 in the Central Jail, Poojapura, Thiruvananthapuram. The detention order relied on three drug cases against the detenue, the last of which, Crime No.48 of 2025 of the Excise Enforcement and Anti Narcotic Special Squad, Kannur, arose from an incident on 24.06.2025. A fourth case, in which he had been convicted, was excluded. The Bench rejected the challenge based on delay and the snapping of the live link, and also found that all documents relied on had been supplied.

WP(Crl.) No. 1448 of 2026 | 2026:KER:88958
Bombay High Court Allowed ·19 Nov 2026 ·Land Acquisition

Bombay HC Remands CIDCO Land Acquisition References, Keeps Valuation Issue Subject to Pending Supreme Court Ruling

The question: What is the relevant date for fixing market value of land acquired under section 126 of the MRTP Act when the declaration came before the RFCTLARR Act and the award after it

The Bombay High Court at Aurangabad has allowed writ petitions filed by CIDCO and quashed a common order of the Maharashtra Land Acquisition, Rehabilitation and Resettlement Authority, Nagpur, dated 16/02/2019. The Authority had held that market value of land acquired under the Maharashtra Regional and Town Planning Act, 1966 (MRTP Act) had to be fixed as on 01/01/2014, the date the 2013 Act came into force, and had sent the matter back to the Land Acquisition Officer for a fresh award. The High Court held that the point is covered by Division Bench rulings in Sahebrao Bhausaheb Kalate v State of Maharashtra and S.N. Desai Hospitalities and Developers LLP v Deputy Collector, under which the relevant date is the date of the declaration under section 126(4) of the MRTP Act, here 22/12/2011. It also held that the Authority has no power to remand a reference to the Land Acquisition Officer. The lands in Gut Nos. 12, 14, 15, 16, 18 and 256 of Village Golwadi, Aurangabad, were acquired for CIDCO for the development of the Waluj area under section 126 of the MRTP Act read with section 6 of the Land Acquisition Act, 1894. The Special Land Acquisition Officer (Special Unit), Aurangabad passed an award on 21/02/2017 for the first set of lands and on 31/07/2018 for Gut No. 256. Unhappy with the compensation, the owners sought references under section 64 of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (RFCTLARR Act). On a preliminary issue they argued that, since the declaration of 22/12/2011 pre-dated the 2013 Act and the award post-dated it, market value should be taken as on 01/01/2014. The Authority agreed.

WP No. 5134 of 2019 and connected petitions | 2026:BHC-AUG:55240