Subscribe

Latest › Delhi High Court › Civil › Contract & Commercial › 28 September 2026

Delhi High Court Notable

Delhi HC: Arbitrator's refusal of price variation despite the contract's formula is patent illegality; award partly set aside

Court
High Court of Delhi
Date of judgment
28 September 2026
Case
O.M.P. (COMM)/182/2019
Parties
M/S. DWARIKA PROJECTS LTD. Vs NEW OKHLA INDUSTRIAL DEVELOPMENT AUTHORITY
Bench
Mini Pushkarna
Outcome
Partly allowed

The court's decision

The Court first set out the limits of Section 34: it is not an appeal, and it does not allow reappreciation of evidence or substitution of a Court's view, but an award can be set aside for patent illegality, including where the arbitrator ignores specific provisions of the contract or takes a view that is not even a possible one.

Original period: the arbitrator had held that Clause 50.1 made the Bill of Quantities rates hold good till completion, so no price variation was available. The Court said he read only the first part of the clause and ignored the qualifying words, even though Clause 50.2 provides a price variation formula for labour, material and fuel, and the tender documents say the quoted prices were subject to adjustment under the Special Conditions. This was not another interpretation but one that made the agreed procedure inoperative, so it was not a possible view.

Extended period: the arbitrator himself noted that Clause 51.2, read with Clause 7.5, allows price variation even where the extension is for the contractor's delay, but then held that the contractor's delay barred it. The Court said the contract distinguishes only how price variation is calculated (the indices on the last date of the original period where the delay is the contractor's), not whether it is payable. Treating delay as a complete bar rewrote the contract and went to the root of the matter. Ramnath International was distinguished, because the contract there expressly barred compensation for extensions, while this one has no such bar.

Delay: the Court upheld the finding that the delay was attributable to the contractor. Electric poles stood on one side of the drain only and were removed on 7 May 2010, with no proof of complete stoppage. No term required SAIL steel, and NOIDA's letter of 21 March 2011 allowed other brands. The arbitrator found no delay in paying bills, and NOIDA's letters from 2010 and 2011 on the slow pace of work were not challenged.

Order: the award was set aside to the extent of Claim 4 for patent illegality, and the parties are at liberty to invoke fresh arbitration to determine the amount of price variation. The petition was partly allowed.

Summary

The Delhi High Court has set aside part of an arbitral award in a road-bridge contract with the New Okhla Industrial Development Authority (NOIDA), holding that the arbitrator's refusal of the contractor's price variation claim was patently illegal because it ignored what the contract itself provides. Justice Mini Pushkarna held that the contract allowed price variation both for the original period and for an extension caused by the contractor's own delay, and that the arbitrator had in effect rewritten the contract. The Court, however, upheld his finding that the delay was the contractor's fault.

Dwarika Projects Ltd. won a tender for the construction of Bridge No. 2 on an irrigation drain between Sectors 78 and 49, Noida, under a contract of 7 December 2009 that required completion within twelve months. The work finished much later, and each side blamed the other. The sole arbitrator's award of 10 December 2018 awarded the contractor Rs 1,02,95,056 on Claims 1, 2 (in part) and 3, with interest and costs, but rejected Claims 4 to 10. The contractor's petition under Section 34 of the Arbitration and Conciliation Act, 1996 was finally confined to Claim 4, its claim of Rs 2,29,43,350 for price variation.

The Court set the award aside to that extent and left the parties free to start fresh arbitration to work out the amount.

The question before the court

What each side argued

Precedents referred to

Provisions referred to

Read the full judgment (PDF) ↗

Official source: High Court of Delhi. The PDF above is a copy from an open dataset of the court's public records.

This summary is prepared for general assistance only. It may contain errors and is not legal advice — rely on the full judgment.

ArbitrationConstruction ContractsPrice VariationPatent Illegality

Related judgments

Delhi High Court Dismissed ·6 Nov 2026 ·Arbitration

Delhi HC: Interest Accrued on Fixed Deposit From Wrongfully Invoked Bank Guarantee Must Go to Contractor, Not DDA

The question: Whether the award, to the extent it denied the company the interest accrued on the fixed deposit made from the encashed performance bank guarantee, suffered from patent illegality warranting interference under Section 34

The Delhi High Court, sitting as a Bench of two Judges, has dismissed an appeal by the Delhi Development Authority against a Single Judge's order that modified an arbitral award. The award had held that DDA was not entitled to invoke the performance bank guarantee given by Jaksons Developers (P) Ltd, but had also said that the interest accrued on the fixed deposit holding the encashed amount would not be released to the company. The Single Judge set aside that part of the award. The Bench, in a judgment by Dr. Justice Aditi Choudhary, agreed that interest on the fixed deposit is the fruit of the principal and must follow it. DDA invited bids for a commercial plot at Twin District Towers, Rohini, for a hotel to house guests during the Commonwealth Games 2010. Jaksons Developers was the successful bidder and a Demand-cum-Allotment Letter was issued on 04.01.2008. The hotel had to be operational within twenty-four months of allotment. On 09.06.2008 the company furnished a performance bank guarantee of Rs. 9,30,00,000, equal to 5% of the bid amount, valid for four years under clause 3.14 of the tender document. Possession was given on 08.09.2008 and the conveyance deed was executed. In May 2010 DDA moved to invoke the guarantee for non-completion within twenty-four months. The company obtained an order under Section 9 of the Arbitration and Conciliation Act, 1996 on 09.06.2010 restraining invocation. The hotel was completed and made operational on 15.09.2010, DDA rejected the application for a completion or occupancy certificate on 21.09.2010, and limited term permission was granted on 29.09.2010. The hotel was used during the Games. An Arbitrator was appointed on 12.05.2011. On 22.10.2013 the Arbitrator, deciding an application under Section 17, vacated the restraint on condition that DDA keep the amount realised on encashment in a fixed deposit in a nationalised bank, to abide the outcome along with interest accrued. The award dated 25.04.2023, with an addendum of 21.05.2023, held DDA not entitled to invoke or encash the guarantee and directed release of Rs. 9,30,00,000 to the company. Claim No. 8 of the company, for 18% interest on the awarded amount, was rejected on the ground of delay attributable to both sides, the Chief Fire Officer and the Delhi Urban Arts Commission, and the addendum said the interest accrued on the guarantee would not be released to the company. DDA's counter claims, including one for interest on the guarantee amount, were all rejected. The company challenged the withheld interest under Section 34 (OMP (COMM) 349/2023). The Single Judge modified the award on 05.05.2026, and DDA appealed under Section 37(1)(c) read with Section 13(1A) of the Commercial Courts Act, 2015.

FAO(OS) (COMM) - 192/2026
Supreme Court Allowed ·12 Oct 2026 ·Arbitration

Clauses name Delhi and Goa: Goa exclusive jurisdiction and Goa hearings make Goa the seat; Delhi High Court could not appoint arbitrator

The question: Whether Delhi or Goa is the juridical seat of arbitration when the arbitration clause mentions both places and the governing law clause gives exclusive jurisdiction to courts in Goa

The Supreme Court has held that where an arbitration clause names two places for the arbitration, one of them cannot automatically be treated as the juridical seat, and the governing law and jurisdiction clause of the agreement must be read to find the parties' intention. On that reading, the Bench of Justice Manoj Misra and Justice Vijay Bishnoi held that Goa was the seat and Delhi merely the venue, and that the Delhi High Court therefore had no jurisdiction to appoint an arbitrator under Section 11(6) of the Arbitration and Conciliation Act, 1996. The judgment is reported as 2026 INSC 1109. The dispute arose from a Franchise Agreement dated 3 August 2023 between Arcis Clean Energy Pvt. Ltd. and Parshva Innovation. Clause 32.4 of the arbitration clause said the precise location of the arbitration shall be within Delhi, while Clause 32.5 said the arbitration proceedings will be held in Goa. Clause 38 submitted the parties to the exclusive jurisdiction of the competent courts in Goa. The respondent proposed a sole arbitrator by notice of 25 March 2025. The appellant rejected the proposal on 19 April 2025. The respondent then moved the Delhi High Court, which by its order of 11 November 2025 appointed an arbitrator and left it to the arbitrator to choose the venue of hearings in consultation with the parties. The appellant came to the Supreme Court against that order. Leave was granted and the appeal was allowed.

C.A. No. 13663/2026
Karnataka High Court Dismissed ·28 Sep 2026 ·Property

Karnataka High Court: non-alienating sharer need not seek formal declaration against sale in partition suit

The question: Whether the appeal of defendant No. 3 survived after his earlier appeal on the same decree was dismissed

The plaintiff's appeal in RFA No. 1530/2020 was allowed and the appeals of defendants Nos. 2 and 3 were dismissed. The plaintiff and defendant No. 1 hold equal shares in suit items 1 and 2. A sharer in a partition suit cannot be non-suited merely because she did not seek a formal declaration that a sale by a family member is not binding on her. The plaintiff sued in 2004 for partition and separate possession of her share in two properties and for mesne profits. Her great grandfather had settled them on her father by a registered deed dated 28.06.1939. The father died intestate in April 1980, leaving the plaintiff and her brother (defendant No. 1). The brother sold item No. 1 to defendant No. 2 in 1998 and, with his children, item No. 2 to defendant No. 3 in 2001, without the plaintiff's consent. The trial Court decreed the suit in part on 30.05.2020. It gave the plaintiff a half share in item No. 2, following an earlier decree against defendant No. 3 that had become final when his appeal, RFA No. 1063/2010, was dismissed. It treated item No. 1 as ancestral and gave the plaintiff a one-fourth share in item No. 1. Three appeals followed: RFA No. 723/2021 by defendant No. 2, RFA No. 1530/2020 by the plaintiff and RFA No. 203/2021 by defendant No. 3, heard together.

RFA/1530/2020