Tahsildar fined Rs. 2,000 for contempt: AP HC says pending appeal and suit were no reason to refuse Form 1(B) when its order had no stay

Court
High Court of Andhra Pradesh
Date of judgment
11 November 2026
Case
CC/1516/2024
Outcome
Allowed

The court's decision

The Court said the factual background of the writ petition need not be gone into in detail. The petitioner's grievance concerned 71 cents in Survey No. 18/8 of Ravivalasa Village, which the petitioner says he bought under the registered sale deed of 4 November 2004, and the Encumbrance Certificate of 11 February 2024 reflects that transaction.

It found from the endorsement of 9 July 2025 that respondent No. 4 was well aware of the order of 18 October 2023, and that after taking charge she had taken no steps to examine the petitioner's claim in the light of the proceedings of 10 April 2025. She took shelter in a pending writ appeal, W.A. No. 594 of 2025, filed by a third party against the writ order, and in the registered sale deed having been executed in the petitioner's favour by his mother-in-law without the knowledge of her three daughters, with a suit pending. The Court pointed out that the same ground, pendency of a civil suit, had been the reason for the earlier rejection that led to W.P. No. 5183 of 2023, where the rejection was faulted. Even in W.A. No. 594 of 2025 it is not the case of respondent No. 4 that the writ order was stayed or suspended, so, knowing the order, she issued the proceedings of 9 July 2025 in a contemptuous manner when she had ample opportunity to examine the claim with reference to the sale deed of 4 November 2004.

The Court added that it had not declared any rights of the parties in the land but had only directed issue of Digital Signed Form 1(B), and that it is settled law that a mere entry in the revenue records does not confer title. There was no impediment to implementing the order, against which the revenue authorities had filed no appeal and and no stay had been granted in the appeal filed by a third party. The endorsement of 9 July 2025 could not be countenanced, and issuing it amounted to a willful and deliberate violation of the order of 18 October 2023, making respondent No. 4 liable to punishment under the Contempt of Courts Act.

On punishment, the Court said that in normal circumstances imprisonment of the contemnor might be directed, but, as respondent No. 4 is a lady officer aged about 61 years, it took a lenient view and imposed a fine of Rs. 2,000, with costs. It cited Sebastian M. Hongray v. Union of India for the view that for violation of orders imprisonment and fine can be imposed and costs can also be levied, and quoted E.T. Sunup v. C.A.N.S.S. Employees Association, where the Supreme Court said that the tendency of government officers to circumvent court orders shows a complete lack of grace in accepting them and cannot be countenanced.

Final order: the Contempt Case was allowed against respondent No. 4 with costs of Rs. 10,000 payable to the petitioner and a fine of Rs. 2,000 payable to the Registrar (Judicial), High Court of A.P., Amaravati, within four weeks from receipt of a copy of the order. In default, the order provides for seven days' simple imprisonment; the operative sentence refers to 'the petitioner', apparently meaning the contemnor. Pending miscellaneous applications stood closed.

Summary

Justice Ninala Jayasurya of the Andhra Pradesh High Court has held the Tahsildar of Bogapuram, impleaded as respondent No. 4, guilty of contempt for issuing an endorsement of 9 July 2025 that refused to implement the Court's order of 18 October 2023 in W.P. No. 5183 of 2023. That order had directed Digital Sign Form 1(B) to be issued for the petitioner's land. The Tahsildar's reasons were a pending writ appeal filed by a third party and a pending civil suit over the sale deed in the petitioner's favour. The Court held that the endorsement willfully and deliberately violated the order, imposed a fine of Rs. 2,000 and costs of Rs. 10,000, saying that in normal circumstances imprisonment of the contemnor may be directed but that it took a lenient view. The order is dated 11 September 2026.

In W.P. No. 5183 of 2023 the Court had set aside an endorsement of 29 July 2022 of the Tahsildar, Bogapuram Mandal, which had rejected the petitioner's request for Digital Sign on Form 1(B) for lands in Ravivalasa Village. It held, following Erukula Uma v. Government of A.P., and by the instructions of the CCLA, that mere pendency of a civil suit, without an injunction, is no ground to reject an application for mutation and a pattadar passbook, and directed the Tahsildar to take necessary action for issuing Digital Sign Form 1(B) in accordance with law and the procedure in vogue, as expeditiously as possible. The order was implemented except for 71 cents in Survey No. 18/8, and the petitioner filed this contempt case.

The Tahsildars in office at different times were brought on record. On 10 April 2025 the Court left it open to the petitioner to approach the Tahsildar with material on title and rights over the 71 cents so that the web land register could be updated. The endorsement of 9 July 2025 followed a grievance application apparently made by his son, and respondent No. 4 was impleaded on 22 January 2026 with a prima facie view that the endorsement amounted to willful defiance.

The question before the court

What each side argued

Precedents referred to

Provisions referred to

Official source: High Court of Andhra Pradesh. Search for the full order on the court's website using the case number given above.

This summary is prepared for general assistance only. It may contain errors and is not legal advice — rely on the full judgment.

Contempt Of CourtLand And RevenueService Of OrdersWrit JurisdictionTahsildar

Related judgments

Delhi High Court Allowed ·18 Nov 2026 ·Tort ★ Editor's pick

Two Children Die After Falling into Open Sewer in Park; Delhi HC Directs DDA and DJB to Pay Compensation

The question: Whether a writ petition for compensation for deaths in an open sewer was maintainable despite the objection of disputed questions of fact and the remedy of a civil suit

The Delhi High Court has allowed two connected writ petitions, filed separately by the respective parent of each of two boys who died on 16 April 2010 after slipping into an open sewer manhole in a DDA park at SU Block, near Double Tanki, Pitampura. Justice Jasmeet Singh held the Delhi Development Authority and the Delhi Jal Board negligent and jointly and severally liable to pay Rs. 11,01,000 (rounded off) in each petition, with 9% simple interest from the date of filing of the petitions, and Rs. 1,00,000 as costs in each petition. The Municipal Corporation of Delhi was held not liable. The children were about 11 and a half years and 12 years nine months old. A PCR call led to FIR No. 142/2010, registered under Section 304A of the Indian Penal Code, 1860. The MCD and the Delhi Jal Board first denied that the site fell within their jurisdiction. In a reply of 22 June 2011 the Delhi Jal Board said the site was an RCC chamber with a raised wall of 4 to 5 feet. The police later filed a cancellation report, which, according to the police respondents, the ACMM, Rohini Courts, accepted on 5 August 2013. The parents learnt of this in 2015, sent notices under Section 80 of the Code of Civil Procedure seeking Rs. 10,00,000 each, and filed the writ petitions in 2016. They sought compensation, interest and costs from the DDA, Delhi Jal Board, MCD, the Investigating Officer, the Commissioner of Police and the Ministry of Home Affairs. The petitions were heard together and judgment, reserved on 13 August 2026, was pronounced on 18 November 2026.

W.P.(C)/317/2016 (with W.P.(C) 284/2016)
Kerala High Court Allowed ·20 Nov 2026 ·Preventive Detention ★ Editor's pick

Article 22(5) Violated by Non-Supply of Detention Order in Malayalam and Failure to Consider Representation: Kerala HC

The question: Whether unexplained delay in issuing the detention order snapped the live link with the last prejudicial activity

The Kerala High Court has set aside an order of preventive detention passed under Section 3(1) of the Prevention of Illicit Traffic in Narcotic Drugs and Psychotropic Substances Act, 1988 (PITNDPS Act), and the Government order confirming it for one year. A Division Bench of Justice Anil K. Narendran and Justice Muralee Krishna S. held that the detention order was not supplied to the detenue in Malayalam, the language recorded in it as known to him, and that a representation sent to the Central Government by the petitioner, his wife, was never considered. Each lapse breached Article 22(5) of the Constitution. The petitioner, wife of the detenue, challenged Ext.P1 order dated 31.03.2026, issued by the Additional Chief Secretary to the Government under Section 3(1), and Ext.P2 order dated 16.09.2026, issued under Section 9(f) read with Section 11, confirming the detention for one year from the date of detention. She also sought a writ of habeas corpus for his release. The detenue was apprehended on 16.07.2026 and has been in detention since 17.07.2026 in the Central Jail, Poojapura, Thiruvananthapuram. The detention order relied on three drug cases against the detenue, the last of which, Crime No.48 of 2025 of the Excise Enforcement and Anti Narcotic Special Squad, Kannur, arose from an incident on 24.06.2025. A fourth case, in which he had been convicted, was excluded. The Bench rejected the challenge based on delay and the snapping of the live link, and also found that all documents relied on had been supplied.

WP(Crl.) No. 1448 of 2026 | 2026:KER:88958
Bombay High Court Allowed ·19 Nov 2026 ·Land Acquisition

Bombay HC Remands CIDCO Land Acquisition References, Keeps Valuation Issue Subject to Pending Supreme Court Ruling

The question: What is the relevant date for fixing market value of land acquired under section 126 of the MRTP Act when the declaration came before the RFCTLARR Act and the award after it

The Bombay High Court at Aurangabad has allowed writ petitions filed by CIDCO and quashed a common order of the Maharashtra Land Acquisition, Rehabilitation and Resettlement Authority, Nagpur, dated 16/02/2019. The Authority had held that market value of land acquired under the Maharashtra Regional and Town Planning Act, 1966 (MRTP Act) had to be fixed as on 01/01/2014, the date the 2013 Act came into force, and had sent the matter back to the Land Acquisition Officer for a fresh award. The High Court held that the point is covered by Division Bench rulings in Sahebrao Bhausaheb Kalate v State of Maharashtra and S.N. Desai Hospitalities and Developers LLP v Deputy Collector, under which the relevant date is the date of the declaration under section 126(4) of the MRTP Act, here 22/12/2011. It also held that the Authority has no power to remand a reference to the Land Acquisition Officer. The lands in Gut Nos. 12, 14, 15, 16, 18 and 256 of Village Golwadi, Aurangabad, were acquired for CIDCO for the development of the Waluj area under section 126 of the MRTP Act read with section 6 of the Land Acquisition Act, 1894. The Special Land Acquisition Officer (Special Unit), Aurangabad passed an award on 21/02/2017 for the first set of lands and on 31/07/2018 for Gut No. 256. Unhappy with the compensation, the owners sought references under section 64 of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (RFCTLARR Act). On a preliminary issue they argued that, since the declaration of 22/12/2011 pre-dated the 2013 Act and the award post-dated it, market value should be taken as on 01/01/2014. The Authority agreed.

WP No. 5134 of 2019 and connected petitions | 2026:BHC-AUG:55240